 Question : 

Load flow study is carried out for... (GETCO 2012)

A. fault calculations

B. stability studies

C. system planning

D. load frequency control


Answer : C


Explanation :

Load flow study is not useful in fault calculations, stability stydies and load frequency control. It is only useful for system planning. 

Decide about which load to turn On and Off for particular time interval can be made by system planning. 

Please comment below for further queries. Thank you! 


Comments

Popular posts from this blog

Explain superposition theorem and use the principle of superposition to find the voltage Vo in the circuit

(Solved) An LVDT is connected to an amplifier of gain 250 the output terminals of which are connected to a 5 V voltmeter. The meter's scale can be read to 1/5th of a division and has 100 divisions in all. Given that a core displacement of 0.5 mm provides an output of 2 mV from the LVDT, find, 1. The sensitivity of the LVDT 2. The sensitivity of the whole system 3. The resolution of the instrument in centimeters

(Solved) A step down DC chopper has a resistive load of R = 15 ohm and input Vdc = 200 V. When the chopper remain ON, it's voltage drop is 2.5V. The chopper frequency is 1 kHz. If the duty cycle is 50%, determine: a) Average output voltage b) RMS output voltage c) Chopper efficiency d) The effective input resistance of the chopper